Project Schedule Acceleration Analysis Using the Fast-Track Method: A Case Study of the Sigi District Prosecutor’s Office Construction
DOI:
https://doi.org/10.33603/jki.v14i2.12856Keywords:
CPM, Fast Track, Microsoft Project, Project AccelerationAbstract
Construction projects are subject to time constraints and involve interdependent activities, making schedule control essential to achieve the planned completion target. This study aims to determine the schedule lag of the Sigi District Attorney’s Office construction project, evaluate the change in project duration after applying the Fast Track method, and analyze its effect on project activities. A quantitative case study approach was applied using project contract documents, the planned time schedule, weekly progress reports, activity durations, and predecessor relationships. The Critical Path Method (CPM) was first used to identify critical activities, while Microsoft Project was employed to model the existing schedule and analyze changes in activity relationships. The analysis showed that, by week 35, the actual cumulative progress reached 96.40%, compared with 99.96% planned progress, resulting in a 3.56% deviation equivalent to a schedule lag of 28 days on the planned S-curve. The 250-day contractual duration covers physical construction work that was completed within 245 days, and this 245-day existing physical schedule was used as the basis for the CPM and Fast Track analysis. Fast Track was then applied through overlapping critical activities in two stages, after two of the three existing critical relationships were found to already exceed 50% overlap and were therefore excluded from further acceleration. The results showed that the physical work duration was reduced from 245 days to 224 days, representing a reduction of 21 days or 8.57% relative to the 245-day existing schedule. In the scheduling model, the acceleration scenario was formulated without additional labor, equipment, or overtime work. However, the number of critical activities increased from four to eleven, indicating the need for more intensive coordination of labor, equipment, and materials. The results demonstrate that Fast Track can be an effective alternative for recovering schedule delays in government building projects.
References
[1] A. Natasya, A. Setiawan, and I. M. Sari, "Analisa Penerapan Manajemen Waktu pada Proyek Pembangunan Masjid di Tlogoanyar Lamongan," Saintis, vol. 1, no. 2, pp. 45–50, 2024.
[2] E. M. Kristia, "Analisis Penyebab Keterlambatan Pelaksanaan Pekerjaan Konstruksi Kategori Excusable Compensable Delays (Studi Kasus Proyek Rumah Susun di DKI Jakarta)," Sainstech, vol. 35, no. 1, pp. 45–52, 2025.
[3] S. Adrianti, H. Hafiz, W. Safitri, and M. Huda, "Analisis Penjadwalan Proyek Pembangunan Saung Serbaguna di Cikarang Menggunakan PERT dan CPM," Jurnal Ekono Insentif, vol. 18, no. 1, pp. 62–73, 2024.
[4] I. G. N. Sunatha, T. I. Praganingrum, N. L. M. A. Pradnyadari, and N. P. O. Larashati, "Analisis Tracking Waktu Penyelesaian Proyek Akibat Terjadinya Contract Change Order (CCO)," Jurnal Ilmiah Kurva Teknik, vol. 12, no. 2, pp. 146–152, 2023.
[5] I. G. A. Diputera, I. P. Y. Hermawan, and N. P. L. M. Yanthi, "Analisis Waktu dan Biaya Percepatan (Fast Track) pada Pembangunan Gedung SKB Kota Denpasar Berbasis Software Microsoft Project," Jurnal Ilmiah Kurva Teknik, vol. 12, no. 1, pp. 38–44, 2023.
[6] Y. B. Mokalu, T. T. Arsjad, and G. Y. Malingkas, "Analisis Percepatan Proyek dengan Menggunakan Metode Fast Track (Studi Kasus: Proyek Pembangunan Mall Pelayanan Publik Manado)," TEKNO, vol. 20, no. 82, pp. 621–629, 2022.
[7] Z. R. Wardana and I. N. D. P. Putra, "Analisis Percepatan Proyek Menggunakan Metode Fast Track dan Metode Crashing pada Proyek Pembangunan Gedung Bertingkat," CIVED, vol. 10, no. 2, pp. 491–500, 2023.
[8] A. S. Tambunan and D. S. Harahap, "Penerapan Metode Fast Track dalam Menganalisis Waktu dan Biaya pada Proyek Pelaksanaan Pengendalian Prasarana Banjir di Kualanamu Kab. Deli Serdang," Buletin Utama Teknik, vol. 19, no. 1, pp. 58–64, 2023.
[9] T. D. Ernandi, A. Gunasti, and T. D. Kuryanto, "Studi Penggunaan Metode Fast Track dalam Rangka Percepatan Proyek Gedung Olahraga Situbondo," Jurnal Smart Teknologi, vol. 7, no. 1, pp. 44–55, 2025.
[10] M. R. Fadlillah, "Analisis Percepatan Waktu pada Proyek Renovasi dan Pengembangan Gedung Kantor SMK Kehutanan Negeri Makassar dengan Menggunakan Metode Fast Track," Tugas Akhir, Program Sarjana Departemen Teknik Sipil, Fakultas Teknik, Universitas Hasanuddin, Gowa, 2023.
[11] A. Irfansyah, S. K. Saptomo, and M. Y. J. Purwanto, "Analisis Peran Pejabat Pembuat Komitmen (PPK) dalam Penanganan Keterlambatan Proyek Pembangunan Gedung Plaza Aspirasi," Jurnal Sosial dan Teknologi (SOSTECH), vol. 6, no. 1, pp. 299–309, 2026.
[12] A. Khiyana, T. Sundari, T. Yulianto, M. W. Nugroho, and A. I. Agung, "Analysis and Risks Fast Track and Crash Program Method on Building Project," Jurnal Pensil: Pendidikan Teknik Sipil, vol. 14, no. 1, pp. 154–168, 2025.
[13] A. Amir, L. Khodeir, and A. K. Abd El-Hameed, "Identification of Key Risks in Fast-Track Construction Projects: A Literature Review," MSA Engineering Journal, vol. 2, no. 2, Art. no. 291869, 2023.
[14] C. Garrido Martins, S. M. Bogus, and V. Valentin, "Perceptions of Construction Risks Due to Fast-Track Activity Overlapping," Eng, vol. 4, no. 4, pp. 2879–2895, 2023.
Downloads
Published
Issue
Section
Citation Check
License
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International License that allows others to share and adapt the work with an acknowledgement of the works authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journals published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Upon receiving the proofs, the Author/Editor agrees to promptly check the proofs carefully, correct any errors, and authorize the publication of the corrected proofs.