Comparison of Scheduling Effectiveness and Cost Performance Using Line of Balance and Gantt Chart Methods: A Case Study of the Denanyar–Sendangrejo Road Project
DOI:
https://doi.org/10.33603/jki.v14i2.12406Keywords:
Cost Efficiency, Line of Balance, Project Duration, Project SchedulingAbstract
The success of a construction project is highly influenced by the accuracy of scheduling and the suitability of cost planning. To prevent project delays and cost overruns, a rescheduling analysis was conducted on the Denanyar–Sendangrejo Road Construction Project using the Gantt Chart and Line of Balance (LoB) methods. This study aims to analyze and determine the effectiveness of project duration in relation to project costs. The analysis was carried out through the calculation of labor-hour requirements, workforce grouping, determination of activity start times, and buffer time allocation. The results indicate that the Line of Balance (LoB) method produces a shorter project duration, requiring only 58 days compared to 77 days using the Gantt Chart method, with an effectiveness value of 24.68%. In terms of cost, the LoB method results in a project cost of IDR 485,430,365.41, which is 0.82% more efficient than the Gantt Chart method, with a cost of IDR 489,430,383.41. Therefore, the Line of Balance (LoB) method is proven to be more effective in reducing project duration and more efficient in minimizing project implementation costs.
References
[1] V. Issue and R. Musa, “JUTIN : Jurnal Teknik Industri Terintegrasi Kajian manajemen pengendalian waktu dan biaya pada proyek relokasi jalan masyarakat berdampak Bendungan Bulango Ulu Provinsi Gorontalo,” vol. 8, no. 1, pp. 753–760, 2025.
[2] S. M. Kalia, A. Utiarahman, M. Y. Tuloli, and E. Srimutianingsikaliagmailcom, “PENERAPAN METODE LINE OF BALANCE PADA PROYEK KONSTRUKSI REPETITIF ( STUDI KASUS : PERUMAHAN GRIYA TUNAS MANDIRI ),” vol. 2, pp. 35–46, 2022.
[3] A. Maddeppungeng et al., “METODE KESEIMBANGAN GARIS ( LINE OF BALANCE ) PADA PENJADWALAN PROYEK REPETITIF Pelaksanaan Proyek Pembangunan Jalur Ganda Kereta Api Kroya – Kutoarjo menggunakan Metode Line of Balance ”. Didapatkan selisih durasi 526 hari dengan penjawalan existing . LoB efektif yang karena,” vol. 14, pp. 88–106, 2022.
[4] F. Supriani, “Analisis Penjadwalan Proyek Pada Pekerjaan Repetitif Dengan Metode Line of Balance (Lob) Dan Precedence Diagram Method (Pdm),” Teknosia, vol. 16, no. 2, pp. 9–19, 2023, doi: 10.33369/teknosia.v16i2.23648.
[5] W. Sudarson, “EVALUASI PENJADWALAN PROYEK DENGAN METODE LINE OF BALANCE ( LOB ) ( Studi Kasus : Hotel Santika Batam ),” vol. 1, no. 2, pp. 92–98, 2020.
[6] I. H. Saputra et al., “OPTIMASI PENJADWALAN WAKTU PROYEK REKONSTRUKSI JALAN RIGID MENGGUNAKAN METODE LINE OF BALANCE ( LOB ) OPTIMASI PENJADWALAN WAKTU PROYEK REKONSTRUKSI JALAN RIGID MENGGUNAKAN METODE LINE OF BALANCE ( LOB ),” vol. 13, no. 2, pp. 67–75, 2025.
[7] R. Susanti and L. Lukman, “Studi Eksplorasi Metode Penjadwalan Pada Proyek Konstruksi (Studi Kasus: Proyek Pembangunan Jalan Tol Semarang-Solo Ruas Ruas Ungaran – Bawen Paket V),” J. Proy. Tek. Sipil, vol. 2, no. 1, pp. 1–3, 2019, doi: 10.14710/potensi.2019.3607.
[8] W. Y. Widiyaningrum, “EFEKTIVITAS MALL PELAYANAN PUBLIK ( MPP ) OLEH DINAS PENANAMAN MODAL DAN PELAYANAN SATU PINTU ( DPMPTSP ) DALAM MENINGKATKAN PELAYANAN PUBLIK DI,” vol. 6, no. November, 2022.
[9] I. Sabariah, S. Syaiful, and N. Ida Hayati, “Analisis Metode Network Planning Dan S-Curve Proyek Konstruksi Di Bogor,” Astonjadro, vol. 1, no. 1, p. 28, 2020, doi: 10.32832/astonjadro.v1i1.782.
[10] Rony K, “PENERAPAN METODE CPM DAN GRANTT CHART UNTUK MENGUKUR EFISIENSI WAKTU (Studi Kasus Pembangunan Rumah Perum GIP Kertosono, Nganju,” pp. 225–239.
Downloads
Published
Issue
Section
Citation Check
License
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International License that allows others to share and adapt the work with an acknowledgement of the works authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journals published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Upon receiving the proofs, the Author/Editor agrees to promptly check the proofs carefully, correct any errors, and authorize the publication of the corrected proofs.