Analysis Of Construction Management On The Ashley Hotel Central Jakarta Development Project

Shilvy Aghniya, Saihul Anwar

Abstract


Construction Management is the process of implementing management functions (Planning, Organizing, Actuating and Controlling) systematically on a project by using existing resources effectively and efficiently in order to achieve project objectives optimally.

Analysis of Construction Management on the Ashley Hotel Central Jakarta Development Project isstartingfromtheanalysisofimplementationmethod,thecalculationoftheworkvolume,thecalculation of the needs of labor, material, and equipment, the calculation of the budget plan, and the time and cost control project with Barchart, S-Curve and Critical Path Method(CPM).

Based on the analysis that has been done with Barchart, S-Curve and CPM, the construction of Ashley Hotel takes 69 weeks with an estimated cost of Rp. 39.091.299.600,00.

Keyword : Construction Management, Barchart, S-Curve, CPM (Critical Path Method).


Full Text:

PDF

References


Lasari, Opi. 2017. Analisis Manajemen Konstruksi Pembangunan RSUD Brebes. Skripsi. Universitas Swadaya Gunung Jati: Cirebon

Widiasanti, Irika., dan Lenggogeni. 2013. Manajemen Konstruksi. Bandung: PT. Remaja Rosdakarya

Husen, Abrar. 2011. Manajemen Proyek.

Yogyakarta: CV. Andi Offset

Haruna, Syahreza. 2015. Analisa Penerapan Manajemen Waktu pada Proyek Pembangunan Gedung Pendidikan Terpadu Politeknik Negeri Manado. Tugas Akhir. Politeknik Negeri Manado : Manado

Hardianto, Agung. 2015. Analisa Pengendalian Manajemen Waktu dan Biaya Proyek Pembangunan Hotel dengan Network CPM (Studi Kasus : Batiqa Hotel Palembang). Naskah Publikasi. Fakultas Teknik Universitas Muhammadiyah Surakarta : Surakarta

Kartikasari,Aprilina.2012.AnalisisNilaiHasil Terhadap Waktu pada Proyek Konstruksi (Studi Kasus pada Proyek Pembangunan Gedung Perkuliahan Fisipol Universitas GadjahmadaYogyakarta).Skripsi.Fakultas teknikUniversitasSebelasMaret:Surakarta

Arianto, Arif. 2010. Eksplorasi Merode Bar Chart, CPM, PDM, PERT, Line of BALANCE dan Time Chainage Diagram dalam Penjadwalan Proyek Konstruksi. Tesis. Fakultas Teknik Universitas Diponegoro: Semarang




DOI: http://dx.doi.org/10.33603/jgst.v3i2.2387

Refbacks

  • There are currently no refbacks.